Mobile County Commission 2000 TRANSPORTATION
PAY-AS-YOU-GO
PROGRAM SUMMARY
DISTRICT 2 PROJECTS
MCR-2000-200
Click on the Project Number for further details on the project. Each road has a brief description of the work to be performed in that project. Each road in each project will also be displayed on a map.
The cost estimate indicated in this segment includes the cost of construction, the engineering design and construction quality assurance fees, the preliminary and construction materials testing, Right-of-Way Acquisition, and Administrative cost for the Program.
DISTRICT 2 PROJECTS |
ROAD NAME |
BEGIN |
END |
LENGTH
MILES |
ESTIMATE |
WORK
TYPE
|
MCR-2000-201 |
City of Mobile Streets |
Duncan St |
Dickenson Ave |
McKay Ave |
0.1 |
|
GDBP |
Dickenson Ave |
Duncan Ave |
Chandler St |
0.1 |
|
GDBP |
|
|
|
0.2 |
$100,000 |
|
MCR-2000-202 |
Lansdown Ct |
Howells Ferry Rd |
E.O.M. |
0.1 |
|
GDBP |
Maple Valley Rd |
Silver Pine Rd |
E.O.M. |
0.2 |
|
GDBP |
Illinois St |
Park Ave |
E.O.M. |
0.3 |
|
GDBP |
Forest St |
Illinois St |
E.O.M. |
0.1 |
|
GDBP |
Vergos Dr N |
Vergos Dr W |
Highland Rd |
0.5 |
|
GDBP |
Vergos Dr S |
Vergos Dr W |
Highland Rd |
0.5 |
|
GDBP |
Vergos Dr W |
Vergos Dr N |
Vergos Dr S |
0.1 |
|
GDBP |
Vergos Ct |
Vergos Dr W |
Greaves Rd |
0.1 |
|
GDBP |
|
|
|
1.9 |
$1,003,000 |
|
MCR-2000-203 |
Weaver Rd |
Wilmer - Georgetown Rd |
E.O.M. |
1.0 |
|
GDBP |
Mitchell Rd |
Lott Rd |
E.O.M. |
0.2 |
|
GDBP |
North Woods Dr |
Coleman Dairy Rd E |
0.5 Mile North |
0.5 |
|
GDBP |
North Woods Dr W |
Hickory Ln |
North Woods Dr |
0.3 |
|
GDBP |
|
|
|
2.0 |
$1,055,000 |
|
MCR-2000-204 |
Cleborne Rd |
Lott Rd |
E.O.M. |
0.5 |
|
GDBP |
Byrd Cemetery Rd |
Lott Rd |
E.O.M. |
0.6 |
|
GDBP |
|
|
|
1.1 |
$638,000 |
|
MCR-2000-205 |
Elmer Turner Rd |
Earlville Rd |
E.O.M. |
0.4 |
|
GDBP |
Malone Rd |
Lott Rd |
1.1 Miles North |
1.1 |
|
GDBP |
Sand Ridge Rd |
Gulfcrest Rd |
Morgan Rd |
0.9 |
|
GDBP |
|
|
|
2.4 |
$1,394,000 |
|
MCR-2000-206 |
Walter Tanner Rd |
Wilmer - Georgetown Rd |
1.4 Miles West |
1.4 |
|
GDBP |
|
|
|
1.4 |
$812,000 |
|
MCR-2000-207 |
Fifth St |
Moffett Rd |
E.O.M. |
0.1 |
|
GDBP |
Third St |
Ave "B" |
Ave "A" |
0.1 |
|
GDBP |
Second St |
Ave "B" |
Ave "A" |
0.1 |
|
GDBP |
Ave "A" |
First St |
E.O.M. |
0.3 |
|
GDBP |
Danner Rd |
Wilmer -Georgetown Rd |
E.O.M. |
0.6 |
|
GDBP |
Thompson Rd |
Wilmer -Georgetown Rd |
E.O.M. |
0.6 |
|
GDBP |
|
|
|
1.8 |
$950,000 |
|
MCR-2000-208 |
Moody Loop Rd N |
Driskell Loop Rd W |
Moody Loop Rd W |
0.5 |
|
GDBP |
Moody Loop Rd S |
Driskell Loop Rd W |
Moody Loop Rd W |
0.5 |
|
GDBP |
Moody Loop Rd W |
Moody Loop Rd N |
Moody Loop Rd S |
0.3 |
|
GDBP |
Moody Loop N Ext |
Moody Loop Rd N |
E.O.M. |
0.1 |
|
GDBP |
Moody Loop S Ext |
Moody Loop Rd S |
E.O.M. |
0.1 |
|
GDBP |
Grandma Driskell Rd |
Moody Loop Rd S |
E.O.M. |
0.3 |
|
GDBP |
|
|
|
1.8 |
$1,045,000 |
|
MCR-2000-209 |
Laco Cooper Rd |
Wilmer Rd |
E.O.M. |
0.7 |
|
GDBP |
Howells Ferry Rd |
Wilmer Rd |
E.O.M. |
1.3 |
|
GDBP |
|
|
|
2.0 |
$1,161,000 |
|
MCR-2000-210 |
Goff Rd |
Wilmer Rd |
E.O.M. |
1.6 |
|
GDBP |
Baxter Rd |
Goff Rd |
E.O.M. |
0.9 |
|
GDBP |
Baxter Rd S |
Goff Rd |
E.O.M. |
0.2 |
|
GDBP |
|
|
|
2.7 |
$1,426,000 |
|
MCR-2000-211 |
Dykes Rd |
Tanner Williams Rd |
E.O.M. |
1.1 |
|
GDBP |
Mission Rd |
Grand Bay Wilmer Rd |
E.O.M. |
0.5 |
|
GDBP |
Frank Williams Rd |
Grand Bay Wilmer Rd |
E.O.M. |
0.6 |
|
GDBP |
|
|
|
2.2 |
$1,159,000 |
|
MCR-2000-212 |
Brown Loop Rd N |
Brown Loop Rd E |
State Line Rd N |
1.3 |
|
GDBP |
Brown Loop Rd E |
Tanner Williams Rd |
Mack Hinton Rd N |
0.5 |
|
GDBP |
|
|
|
1.8 |
$1,045,000 |
|
MCR-2000-213 |
Watts Rd |
State Line Rd N |
E.O.M. |
0.3 |
|
GDBP |
Section Line Rd |
State Line Rd N |
Cemetery Rd |
1.0 |
|
GDBP |
Guy Williams Rd |
State Line Rd S |
E.O.M. |
0.6 |
|
GDBP |
Sam Robinson Rd |
Tanner Williams Rd |
E.O.M. |
0.4 |
|
GDBP |
|
|
|
2.3 |
$1,214,000 |
|
MCR-2000-214 |
Carr Ln |
Moffett Rd |
E.O.M. |
0.1 |
|
GDBP |
Old Howells Ferry Rd |
Brannon Rd |
E.O.M. |
0.7 |
|
GDBP |
Ward Rd |
End of Pavement |
Ward Rd W |
0.8 |
|
GDBP |
|
|
|
1.6 |
$844,000 |
|
MCR-2000-215 |
Glenwood Rd |
End of Pavement |
Cuss Fork Rd |
1.9 |
|
GDBP |
Cuss Fork Rd |
Glenwood Rd |
Begin Pavement |
0.1 |
|
GDBP |
|
|
|
2.0 |
$1,154,000 |
|
|
|
|
|
|
|
|
|
|
|
|
|
DISTRICT 2 TOTALS: |
27.2 |
$15,000,000 |
|
COUNTY WIDE | DISTRICT 1 | DISTRICT 2 | DISTRICT 3
BACK TO PAY-AS-YOU-GO PROJECTS INDEX
Web page design and hosting by Site One on the Internet. Copyright© 2001.
TYPE OF WORK DEFINITIONS |
ADL: |
ADDITIONAL LANES: This may include patching, leveling, milling, resurfacing, shoulder work, traffic control installation, intersection improvements, drainage improvements, utility relocations, and right-of-way, and/or drainage easement acquisitions. |
W&R: |
WIDENING & RESURFACING - This may include widening of existing pavement, patching, leveling, milling, resurfacing, shoulder work, paving of a portion of the shoulder, traffic control installation, intersection improvements, utility relocation, and right-of-way and/or drainage easement acquisitions. |
R: |
RESURFACE - This may include patching, leveling, milling, resurfacing of the existing width of paved road, minor drainage improvements, traffic control installation, utility relocations, intersection improvements, and right-of-way and/or drainage easement acquisitions. |
GDBP: |
GRADE, DRAIN, BASE & PAVE - This may include clearing, grubbing, grade, drain, base, pave, guardrail, intersection improvements, pavement markings, utility relocations, and right-of-way and/or drainage easement acquisitions. |
BACK TO TOP OF PAGE
MCR-2000-000 PROJECT NOTES: |
001,003,005 NOTE I : |
The Administration of these projects will be performed by the Alabama Department of Transportation. Project 001 will be funded with 80% Federal Funds, 10% State Funds and 10 % County 2000 Transportation Pay-As-You-Go funds. Projects 003 and 005 will be funded by 80% Federal Funds and 20% County 2000 Transportation Pay-As-YouGo Funds. |
002 NOTE 2: |
The Administration of the segment of the project involving Federal Funds will be performed by the Alabama Department of Transportation. Part of the project will be funded with 80% Federal Funds and 20% County 2000 Transportation Pay-As-You-Go Funds. The remaining segment will be funded with County 1996 and 2000 Transportation Pay-As-You-Go Funds. |
004 NOTE 3: |
The Administration of the construction of this project will be performed by the Alabama Department of Transportation. The project will be funded with 80% Federal Funds and 20% County 1996 and 2000 Transportation Pay-As-You-Go Funds. |
101 NOTE 4: |
The Administration of this project will be performed- by the City of Mobile's Engineering Department. The project will be funded by the city of Mobile with a maximum of $600,000 reimbursement of construction by the County 2000 Transportation Pay-As-You-Go Funds. |
301 NOTE 5: |
The Administration of this project will be performed by the City of Mobile's Engineering Department. The project will be funded by the City of Mobile with a maximum of $300,000 reimbursement of the construction cost by the County 2000 Pay-As-You-Go Funds. |